Scope:

Provide Test Support to remove and replace six (6) 220kV CCVT’s which includes cutting the old CCVT’s in the clear, testing all new cables, grounding, and CCVT’s, relay tests, and in-service. Update station prints and create as-built package.

More Projects

EMP Shielded MEER Foundation (2023)

EMP Shielded MEER Foundation (2023)

Civil
12kV, 22kV, 66kV
Switchrack Installation (2023)

Switchrack Installation (2023)

Civil, Electrical
66kV, 220kV
Hydroelectric Powerhouse Test Support (2023)

Hydroelectric Powerhouse Test Support (2023)

Test
220kV
Substation Electrical Installation (2023)

Substation Electrical Installation (2023)

Electrical
34.5kV, 220kV
Substation Build (2023)

Substation Build (2023)

Civil, Electrical, Test
12kV, 66kV
Substation Wall (2022)

Substation Wall (2022)

Civil
Scroll to Top