Sharp Substation
Anaheim, CA
Sharp Substation MEER Building
Customer:
City of Anaheim
Date:
06/2021
Scope:
Contract with Trachte to procure MEER building for customer.
Clear and grub area, survey and grade area for new MEER building.
Install MEER foundation including built in trench systems and stairs.
Coordinate traffic control and delivery of three (3) piece building and restroom being shipped in three (3) oversize loads.
Use a crane to pick and set building pieces and restroom on new foundations.
Install building and secure to the foundation, reinstall facilities and electrical systems including grounding and cable tray.
Install back up batteries for MEER equipment.
Install restroom on new foundations and make final plumbing connection.
More Projects
Lighthipe Substation
Southern California Edison
12kV, 22kV, 66kV
Big Creek 3 Hydroelectric Powerhouse
Southern California Edison
220kV
Windsor Hills Substation
Southern California Edison
4kV, 16kV, 66kV
Barren Ridge Substation
LADWP
34.5kV, 220kV
Medicine Substation
Southern California Edison
12kV, 66kV
Del Amo Substation Fence
Southern California Edison
View All Projects
Scroll to Top
Home
About
Our Team
Careers
Services
Projects
Blog
Follow Us
Facebook
Linkedin
Employee Portal
[email protected]
TEL: 714-698-0930
FAX: 714-643-6003
174 E Liberty Ave., Anaheim, CA 92801
Send us a message
Name
Email
Message
Send
Follow Us
Facebook
Linkedin