Rio Hondo

SCE Rio Hondo, Commerce, USA

Rio Hondo

Customer:
Southern California Edison
Load:
kV
Date:
09/2017
Scope:
  • Demo’d 5,800’ of chain link fencing.
  • Graded entire perimeter.
  • Excavated and poured 2’ deep x 5,800’ long grade beam.
  • Installed 5,800’ of BETA Guardian 5,000 fencing, barbed wire on top of each fence post, 11,600’ of 4/0 ground grid and (2) 20’ swing gates.