Laguna Bell

Commerce, CA

Laguna Bell

Customer:
Southern California Edison
Load:
kV
Date:
10/2018
Scope:
  • Demo existing switchboard panels, RTU and interface panels.
  • Install nine (9) Relay Racks, eighteen (18) GE C60 Relays, DFR, RTU, four (4) Interface panels and cable tray.
  • Pull and terminate all associated cables.
  • Install ten (10) OIC Cabinets and new foundations, 750’+ conduit and 4/0 grounding.