Hinson Substation

Long Beach, CA

Hinson Substation

Customer:
Southern California Edison
Load:
220kV
Date:
09/2020
Scope:
  • Install one (1) A Transformer Bank Foundation, nine (9) Tie Down Foundations, six (6) CCVT Foundations, 500’ 4/0 Ground Grid and all associated conduits.
  • Install one (1) 220kV Transformer Bank, all primary and secondary wiring, thirteen (13) Relay Racks, 10,000’+ of control cables and all associated wiring.
  • Support Test Crew for in-service.