Estero Substation
Oxnard, CA
Estero Substation
Customer:
Southern California Edison
Load:
16kV, 66kV
Date:
05/2023
Scope:
Replace two (2) 66/16kV Transformer Banks with new 28MVA Transformer Banks.
Replace two (2) Potential Transformers (PT).
Replace four (4) circuit breakers and three (3) sets of group operated disconnect switches at each 66kV line position.
Add two (2) sets of bus sectionalizing disconnect switches.
Replace one (1) capacitor bank 16kV and add one (1) set of current limiting reactors (CLRs).
More Projects
Lighthipe Substation
Southern California Edison
12kV, 22kV, 66kV
Big Creek 3 Hydroelectric Powerhouse
Southern California Edison
220kV
Windsor Hills Substation
Southern California Edison
4kV, 16kV, 66kV
Barren Ridge Substation
LADWP
34.5kV, 220kV
Medicine Substation
Southern California Edison
12kV, 66kV
Del Amo Substation Fence
Southern California Edison
View All Projects
Scroll to Top
Home
About
Our Team
Careers
Services
Projects
Blog
Follow Us
Facebook
Linkedin
Employee Portal
[email protected]
TEL: 714-698-0930
FAX: 714-643-6003
174 E Liberty Ave., Anaheim, CA 92801
Send us a message
Name
Email
Message
Send
Follow Us
Facebook
Linkedin