Edwards Substation

Mojave, CA

Edwards Substation

Customer:
EPC Services
Load:
230kV, 34.5kV
Date:
05/2022
Scope:
  • Install one (1) drop-in MEER Building.
  • Install twenty-two (22) 34.5kV collection positions including: twenty-two (22) 34.5kV CB’s, twenty-nine (29) 34.5kV CB’s, twenty-two (22) Collection Units and associated buses and structures.
  • Install seven (7) 230kV CB’s and seven (7) 230kV disconnects including associated buses and structures.
  • Install five (5) 230kV/34.5kV Transformers.
  • Install five (5) static masses.