Devers

North Palm Springs, CA

Devers

Customer:
Southern California Edison
Load:
500kV, 220kV
Date:
05/2019
Scope:

To increase system reliability by revising conductor slack; CCVT mounting; revising 500 kV and 220kV tie downs; provide bracing; and improve anchorage in accordance with the latest seismic mitigation recommendations.

More Projects

Lighthipe Substation

Southern California Edison
12kV, 22kV, 66kV

Windsor Hills Substation

Southern California Edison
4kV, 16kV, 66kV

Barren Ridge Substation

LADWP
34.5kV, 220kV

Medicine Substation

Southern California Edison
12kV, 66kV

Del Amo Substation Fence

Southern California Edison

Estero Substation

Southern California Edison
16kV, 66kV