Project description

Customer: Southern California Edison
Date: 1/28/2015 through 4/3/2015
Load: kV

Scope: 

    • Installation of one (1) 15’x30’ ATS Foundation, 1000’ of six (6) 5” PVC Duct Bank, two (2) three-phase 1000A ATS
    • Pull and terminate all associated power cables.
    • Demo 1S SL&P and 2S SL&P.
    • Demo existing 1S SL&P and 2S SL&P foundations.
    • Install two (2) vaults for SL&P pad mounted transformers including all associated conduits and grounding.
    • Install primary and secondary cables for SL&P transformers.
    • Install new ATS foundation including eight (8) 5” PVC duct banks.
    • Install two (2) three-phase 1000A rated ATS #1 and #2.
    • Install SPC panel and wire from ATS switches.
    • Pull secondary cables from 1S SL&P and 2S SL&P from main CB to ATS switches.
    • All work done under OSHA confined space entry rules.