Customer: Southern California Edison
Date: 10/27/14 – 11/27/14

Scope:

  • Installation of 66kV Circuit Breakers, Gang-Operated Disconnect Switches, Horizontal Disconnect Switches, 66kV Operating and Transfer Busses, Line PT’s, all associated conductoring and grounding.
  • Remove and replace Three (3) 220/66kV Transformer Banks, including all associated primary conductoring, secondary wiring, and grounding
  • Install one (1) 18’x 12’x 8’ vault with manhole.
  • Encase and slurry eight (8) 5” PVC conduits form power cable trench to new vault (400’)
  • Encase and slurry nine (9) 5” PVC conduits form new vault to fence line (400’).
  • Rock Dust 100’ x 80’ area to meet SCE standards.