Our Projects

Project description

Customer: Southern California Edison
Date: 1/23/2012 – 3/23/2012
Load: 66kV

Scope:

  • Install one (1) 66kV circuit breaker and conductor.
  • Install three (3) sets of 66kV disconnects.
  • Install one (1) line PT.
  • Modify existing dead end structure to accommodate 66kv revenue metering units.
  • Install three (3) 66kV revenue metering units.
  • Install three (3) operating bus PTs and associated disconnects.
  • Pull all new homerun cables.
  • Install four (4) new 19” Relay Racks.
  • Install all yard lighting.
  • Subcontracted Work:
    Foundation installation and removal. Underground conduit and grounding.